252 Attunga Road Yowie Bay
SP 62666 Yowie Bay Sutherland Shire New South Wales
Verdict
Public record: 1 tribunal matter, no building-work orders. A reasonable pre-screen, but not the full picture, the financials and minutes that decide the purchase are in the report, not the registers. Read it, and obtain a section 184 strata search, before you bid.
Cost exposure
Indicative, itemised estimate of what one average lot here could face, built only from this scheme's public-record signals. Indicative ranges, not this building's actual figures, and not financial advice.
Elevated- $28,700
Serious building-defect rectification
Indicative per-lot serious-defect rectification levies (NSW Serious Defects in Residential Apartments research report, 2021; strata special-levy reporting). Scaled for: 1 matter.
- $3,000
Tribunal and legal costs
Indicative per-lot share of tribunal and legal costs in a strata dispute (NCAT).
Litigation · 1 matter
Bailey & Anor v Owners Corporation of Strata Plan 62666 [2011] NSWCA 293
Building defects NSWCA 15 September 2011
BUILDING AND CONSTRUCTION - claim of alleged defective work - limitation period - jurisdiction of Consumer, Trader and Tenancy Tribunal to hear and determine building claims - Home Building Act 1989, s48K(7) STATUTORY CONSTRUCTION - statutory warranties as to residential building work - whether landscaping work is "residential building work" - Home Building Act 1989, s 18B - whether evidence of other "residential building work" ADMINISTRATIVE LAW - judicial review of
Decisions naming this scheme, from NSW Caselaw (NCAT and the courts). The quoted line beneath each is the decision's own catchwords; the topic tag is our grouping of those words. Whether a matter helped or hurt the scheme is not assessed here.
Statutory-warranty outlook
- Structural cover
- Likely expired · est. expiry 16 May 2007
- Non-structural cover
- Ran to 16 May 2007
A single 7-year warranty period applies because the scheme was registered before the 1 February 2012 reform. Estimated from the registration date, not the completion date or building contract, so treat the dates as indicative.
Evidence ledger
Registry-backed record: matched to a scheme on the register by its plan number.
| Checked | Found | Match | Last checked |
|---|---|---|---|
| Registry and parcel | NSW Strata Hub, with geometry | Direct | Awaiting first run |
| Governance: AGM, managing agent, annual reporting | Not yet checked | Not matched | Not harvested here yet |
| Litigation: NCAT and courts | 1 matter | Direct | 28 June 2026 |
| Levies and financials | Not yet checked | Not matched | Not in the public record |
| Defects and building-work orders | Checked, none found | Direct | 28 June 2026 |
| Fund balances, current levies, minutes, defects not yet litigated | Not on the public record | Not matched | Never in the public record |
What was checked, what it found, how strong the match, and when each source last ran. A source that has not run here yet reads as not checked, never as checked and clear.