Verdict
Public record: 3 tribunal matters, no building-work orders. A reasonable pre-screen, but not the full picture, the financials and minutes that decide the purchase are in the report, not the registers. Read it, and obtain a section 184 strata search, before you bid.
Cost exposure
Indicative, itemised estimate of what one average lot here could face, built only from this scheme's public-record signals. Indicative ranges, not this building's actual figures, and not financial advice.
Low- $4,300
Tribunal and legal costs
Indicative per-lot share of tribunal and legal costs in a strata dispute (NCAT). Scaled for: 3 matters.
Litigation · 3 matters
The Owners-Strata Plan 47027 v McGinn [2018] NSWSC 1230
Management and meetings NSWSC 8 August 2018
LAND LAW – strata title – owners corporation – meetings of owners corporation – validity of general meeting – resolutions of meeting invalid where chairperson not validly elected and not all lot owners invited to attend or vote – injunction in aid of a statutory right – proper administration of owners corporation interfered with – defendant restrained from holding herself out or acting as a member of strata committee unless and until duly elected
The Owners - Strata Plan No. 47027 v Peter Clisdell Pty Ltd (No. 2) [2018] NSWCATAP 46
Costs and procedure NSWCATAP 15 February 2018
Costs - special circumstances, proceedings dismissed as incompetent, cost claimed where no legal representation at hearing, exercise of discretion where substantive issues raised on appeal not resolved.
Owners Corporation SP 47027 v Peter Clisdell Pty Ltd [2017] NSWCATAP 188
Other NSWCATAP 20 September 2017
Strata Schemes Management Act- commencement of proceedings on behalf of Owners Corporation; rule in Foss v Harbottle Application by interested person- scope of s 226(1)(b) of the Strata Schemes Management Act 2015 (NSW);
Decisions naming this scheme, from NSW Caselaw (NCAT and the courts). The quoted line beneath each is the decision's own catchwords; the topic tag is our grouping of those words. Whether a matter helped or hurt the scheme is not assessed here.
Statutory-warranty outlook
- Structural cover
- Likely expired · est. expiry 9 June 2001
- Non-structural cover
- Ran to 9 June 2001
A single 7-year warranty period applies because the scheme was registered before the 1 February 2012 reform. Estimated from the registration date, not the completion date or building contract, so treat the dates as indicative.
Evidence ledger
Registry-backed record: matched to a scheme on the register by its plan number.
| Checked | Found | Match | Last checked |
|---|---|---|---|
| Registry and parcel | NSW Strata Hub, with geometry | Direct | Awaiting first run |
| Governance: AGM, managing agent, annual reporting | Not yet checked | Not matched | Not harvested here yet |
| Litigation: NCAT and courts | 3 matters | Direct | 28 June 2026 |
| Levies and financials | Not yet checked | Not matched | Not in the public record |
| Defects and building-work orders | Checked, none found | Direct | 28 June 2026 |
| Fund balances, current levies, minutes, defects not yet litigated | Not on the public record | Not matched | Never in the public record |
What was checked, what it found, how strong the match, and when each source last ran. A source that has not run here yet reads as not checked, never as checked and clear.